Farming Zone Subdivisions - Ararat
Gary
1 year
Ararat
Project Included
PROJECT OVERVIEW
- This site consisted of 23 lots in Farming Zone and due to strategic planning at Ararat and council policy we were given pre-approval to re subdivide the 23 lots to 20 lots.
- Part of the site was revised as it was withing the area that Department of Transport are placing the new Ararat bypass.
- DELWP approved the consequential removal after a revision.
- Timing this application was lengthy due to the size and delays with lack of council staff leading to a time frame of 1 year to complete all reports and gain approval.
- The site had many waterways, dams inundation and slopes with good access to road and borders of remnant vegetation under a Vegetation Protection Overlay.
- Application was approved.